D.W. WILBURN, INC.

     (Now in progress. Check regularly for updates.) What was originally planned to be a renovation project is now the construction of a new Tates Creek High School to replace the existing school. The project broke ground in June of 2020 and is expected to be completed in 2.5 to 3 years. The construction includes a new 358,018 new high school building which includes a tornado shelter in the basement as well as a 9,544 sf Fieldhouse including batting cages, public toilettes, and concessions for the softball and baseball program.

Progress Update:

-Brickwork has begun on the Area B Classroom Wing with completion expected by July 16th. The roof dry-in process has also begun and installation of metal roof panels is expected to begin this month as well.

-Bearing walls continue being installed to the roof

-Installation of the air barrier continues and brickwork for the Area B CLassroom Wing will begin in June

-Ceiling work continues in the lower levels and main levels of the basement, including HVAC ductwork, plumbing piping, sprinkler piping, and electrical piping

-Concrete work began at the Field House and the installation of topsoil on the baseball and softball fields continues. In addition, delivery has started for the special infield dirt.

Tates Creek Photo 49 (05-20-21)
Tates Creek Photo 48 (05-20-21)
Tates Creek Photo 40-B(05-01-21)
Tates Creek Photo 50 (05-20-21)
Tates Creek Photo 47 (03-10-21)
Tates Creek Photo 46 (03-10-21)
Tates Creek Photo 44 (03-10-21)
Tates Creek Photo 43 (03-10-21)
Tates Creek Photo 39 (01-22-20)
Tates Creek Photo 40 (01-22-20)
Tates Creek Photo 38 (12-22-20)
Tates Creek Photo 37 (12-22-20)
1/3